Open cable trench at a commercial yard, medium-voltage cable in the sand, warning barriers

Site Development

The connection sits at the start of the project, not at the end.

We handle grid information, connection request, permitting and construction — one contract partner for the entire site.

Starting point

The limiting factor is the grid connection, not the vehicle.

Connection commitments take six to twenty-four months depending on the grid operator. Whoever applies early moves forward the point at which the fleet can run.

Week 0–10
to application
25+ countries
installations by Quibo Energy
10 years
WARRANTY ON THE INSTALLATION'S TECHNOLOGY

The pace

Two stages we can commit to.

OUR PACE Initial consultation Analysis Application Financing framework WEEK 0 TO WEEK 10 GRID OPERATOR’S PACE varies greatly by region Permitting design, funding application, execution planning and procurement continue A mobile solution is available for this period → OUR PACE Construction Acceptance binding financing commitment CONTAINER DELIVERY APPROX. 3 MONTHS Waiting does not get shorter if you start later — it only starts later. We can commit to two stages. The middle belongs to the grid operator and takes six to twenty-four months, depending on the region.

Week 0 to 2 — Intake. We record load profile, fleet plan and site. From this it follows how much power the yard will need in future and when.

Week 2 to 6 — Grid information and sizing. We ask the grid operator what the connection can provide and size storage and charging points accordingly.

Week 6 to 10 — Application. The connection request goes out, and the financing framework is in place.

After that — the grid operator's pace. During this time, permitting design, funding application, execution planning and procurement continue. At the end come construction, commissioning and acceptance; maintenance afterward runs through CATL's European service network.

The connection

What we do with the grid operator for you.

The grid connection decides the schedule, not the technology. We run the process from start to finish: Grid information — what is actually available at the site. Connection request — the formal application with the capacity value we derive from your load profile. Point of connection — exactly where feed-in and offtake occur, and what that means for the routing across your property.

In parallel, everything not tied to the grid operator keeps moving: permitting design, funding application, execution planning and procurement. That is why the waiting time loses its sting — it is not a pause, but the time in which everything else gets finished.

With separate contracts, each trade owes its deliverable. The general contractor owes the result.

Responsibility

Three parties, one responsibility.

YOU Site and fleet Connection contract Handover EVS-Q Analysis, sizing, application documents Permitting design, procurement Construction and acceptance GRID OPERATOR Review and connection commitment Meter installation Initial consultation Connection commitment Inbetriebnahme The dashed section belongs to the grid operator — its duration varies by region.

A charging site rarely fails because of the technology. Often, however, it fails because of coordination.

Next step

The site first. Then the numbers.